Parties
Name
|
Chappell Coal Company Inc
|
Role
|
Operator
|
Start Date
|
1980-01-03
|
End Date
|
1981-07-31
|
|
Name
|
Charolais Corp
|
Role
|
Operator
|
Start Date
|
1981-08-01
|
End Date
|
1997-03-06
|
|
Name
|
Barmac Coal Inc
|
Role
|
Operator
|
Start Date
|
1979-03-01
|
End Date
|
1980-01-02
|
|
Name
|
Black Hills Coal Inc
|
Role
|
Operator
|
Start Date
|
2000-07-01
|
|
Name
|
Centennial Resources Inc
|
Role
|
Operator
|
Start Date
|
1997-03-07
|
End Date
|
2000-06-30
|
|
Name
|
Gary Wayne Johnson
|
Role
|
Current Controller
|
Start Date
|
2000-07-01
|
|
Name
|
Black Hills Coal Inc
|
Role
|
Current Operator
|
|
Accidents
Accident Date |
2001-04-26
|
Degree Inhury |
DAYS AWAY FROM WORK ONLY
|
Accident Type |
Fall from machine
|
Ocupation |
Coal/ore shovel operator, Shoveler, Power shoveler
|
Narrative |
OPERATOR WAS CLIMBING ON BACKHOE PERFORMING HIS PRE-SHIFT INSPECTION, SLIPPED & FELL APPROX. 5' TO THE GROUND LANDING ON HIS LEFT SHOULDER.
|
|
Accident Date |
2000-12-11
|
Degree Inhury |
DAYS AWAY FROM WORK ONLY
|
Accident Type |
Struck against a moving object
|
Ocupation |
Truck driver
|
Narrative |
WALL FELL ON LEFT SIDE OF CAB BECAUSE OF WET CONDITIONS. EE WAS TAKEN TO HOSPITAL AT REGIONAL MEDICAL CENTER RELEASED WITH BRUISED.
|
|
Accident Date |
2000-11-12
|
Degree Inhury |
NO DYS AWY FRM WRK,NO RSTR ACT
|
Accident Type |
Struck by... NEC
|
Ocupation |
Maintenance man, Mechanic, Repair/Serviceman, Boilermaker, Fueler, Tire tech, Field service tech
|
Narrative |
CLEANING WHEEL RUST FROM WHEEL WIND BLOWING CAUSED RUST TO BLOW INTO EYE.PIECE OF RUSH HAD TO BE REMOVED FROM EYE Y
|
|
Accident Date |
2000-03-20
|
Degree Inhury |
DAYS AWAY FROM WORK ONLY
|
Accident Type |
Struck by... NEC
|
Ocupation |
Maintenance man, Mechanic, Repair/Serviceman, Boilermaker, Fueler, Tire tech, Field service tech
|
Narrative |
EE WAS REPLACING U-JOINT IN DRIVE LINE AND HIT HIS THUMB W/HAMMER CAUSING AN OPEN WOUND REQUIRING STITCHES.
|
|
Inspections
Start Date |
2001-10-01
|
End Date |
2001-12-12
|
Activity |
Regular Inspection
|
Number Inspectors |
1
|
Total Hours |
23
|
|
Start Date |
2001-05-17
|
End Date |
2001-06-18
|
Activity |
RESP DUST TECH INSP - SURFACE MINES
|
Number Inspectors |
1
|
Total Hours |
19.5
|
|
Start Date |
2001-04-16
|
End Date |
2001-09-24
|
Activity |
Regular Inspection
|
Number Inspectors |
1
|
Total Hours |
66
|
|
Start Date |
2001-03-19
|
End Date |
2001-03-30
|
Activity |
RESP DUST TECH INSP - SURFACE MINES
|
Number Inspectors |
1
|
Total Hours |
16
|
|
Start Date |
2001-02-27
|
End Date |
2001-03-09
|
Activity |
SPOT INSPECTION
|
Number Inspectors |
2
|
Total Hours |
19.5
|
|
Start Date |
2000-10-02
|
End Date |
2001-03-30
|
Activity |
Regular Inspection
|
Number Inspectors |
1
|
Total Hours |
218.5
|
|
Start Date |
2000-09-05
|
End Date |
2000-10-25
|
Activity |
RESP DUST TECH INSP - SURFACE MINES
|
Number Inspectors |
1
|
Total Hours |
28.5
|
|
Start Date |
2000-04-03
|
End Date |
2000-09-18
|
Activity |
Regular Inspection
|
Number Inspectors |
1
|
Total Hours |
149.5
|
|
Start Date |
2000-03-17
|
End Date |
2000-04-06
|
Activity |
ELECTRICAL INSPECTION
|
Number Inspectors |
1
|
Total Hours |
24
|
|
Start Date |
2000-03-08
|
End Date |
2000-03-08
|
Activity |
RESP DUST TECHNICAL INVESTIGATION
|
Number Inspectors |
1
|
Total Hours |
2
|
|
Start Date |
2000-03-08
|
End Date |
2000-03-08
|
Activity |
NOISE TECHNICAL INVESTIGATION
|
Number Inspectors |
1
|
Total Hours |
8.5
|
|
Start Date |
2000-01-05
|
End Date |
2000-01-05
|
Activity |
RESP DUST TECHNICAL INVESTIGATION
|
Number Inspectors |
1
|
Total Hours |
8
|
|
Productions
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2002
|
Annual Hours
|
11881
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
12
|
Avg. Employee Hours
|
990
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2001
|
Annual Hours
|
98558
|
Annual Coal Prod
|
481997
|
Avg. Annual Empl.
|
55
|
Avg. Employee Hours
|
1792
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2000
|
Annual Hours
|
180761
|
Annual Coal Prod
|
908644
|
Avg. Annual Empl.
|
77
|
Avg. Employee Hours
|
2348
|
|
Sub-Unit Desc
|
MILL OPERATION/PREPARATION PLANT
|
Year
|
2000
|
Annual Hours
|
15732
|
Avg. Annual Empl.
|
14
|
Avg. Employee Hours
|
1124
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2000
|
Annual Hours
|
1082
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
1082
|
|
|