Search icon

Coal Equity, Inc.

Company Details

Name: Coal Equity, Inc.
Legal type: Foreign Corporation
Status: Inactive
Standing: Bad
Profit or Non-Profit: Profit
File Date: 06 May 2014 (11 years ago)
Organization Date: 10 Feb 2003 (22 years ago)
Authority Date: 06 May 2014 (11 years ago)
Last Annual Report: 15 Apr 2021 (4 years ago)
Organization Number: 0886583
Principal Office: 7697 Innovation Way, Suite 200, Mason, OH 45040
Place of Formation: OHIO

Registered Agent

Name Role
KY SECRETARY OF STATE Registered Agent

CEO

Name Role
Ramesh Malhotra CEO

Director

Name Role
Ramesh Malhotra Director

Filings

Name File Date
Revocation of Certificate of Authority 2022-10-04
Annual Report 2021-04-15
Annual Report 2020-02-28
Annual Report 2019-05-30
Annual Report 2018-04-17
Annual Report 2017-05-01
Annual Report 2016-06-30
Annual Report 2015-06-30

Mines

Mine Name Type Status Primary Sic
Placer Processing Plant #1 Facility Temporarily Idled Coal (Bituminous)
Directions to Mine Prestonsburg field office to US23N. Travel towards Catlettsburg, KY. At the old SNR River Ops plant, turn right onto old US23. Travel approximately 1 mile. The facility mine site is on the right.

Parties

Name Coal Equity Inc
Role Operator
Start Date 2001-11-19
Name Boyd County Coal Co
Role Operator
Start Date 1975-03-31
End Date 1978-02-28
Name Placer Coal Inc
Role Operator
Start Date 1978-03-01
End Date 2001-11-18
Name Coal Equity Inc
Role Current Controller
Start Date 2001-11-19
Name Coal Equity Inc
Role Current Operator

Accidents

Accident Date 2011-10-18
Degree Inhury DAYS AWAY FROM WORK ONLY
Accident Type Struck against stationary object
Ocupation Front-end loader, Scraper-loader operator, Pan operator, Payloader, Scraper rig operator
Narrative EE was walking to office to go home stepped on about 2 gravel and twisted ankle (right). Came to office & told me (another ee) what had happened and said it was a little sore. Called in the next morning and couldn't walk on it. Had it x-rayed and it was cracked.
Accident Date 2000-02-09
Degree Inhury DYS AWY FRM WRK & RESTRCTD ACT
Accident Type Struck by... NEC
Ocupation Warehouseman, Bagger, Palletizer/Stacker, Store keeper, Packager, Fabricator, Cleaning plant operator
Narrative EMPLOYEE WAS LIFTING BARGE KICK-OUT COME-A-LONG WHEN THE LEVER SLIPPED FROM RIGHT HAND AND HIT LEFT FOREARM.

Inspections

Start Date 2024-10-17
End Date 2024-10-17
Activity Spot Inspection
Number Inspectors 1
Total Hours 8
Start Date 2024-09-09
End Date 2024-09-09
Activity Regular Safety and Health Inspection
Number Inspectors 1
Total Hours 8
Start Date 2024-09-04
End Date 2024-09-04
Activity Spot Inspection
Number Inspectors 1
Total Hours 7.5
Start Date 2024-05-22
End Date 2024-05-22
Activity Special Emphasis Programs
Number Inspectors 1
Total Hours 2.5
Start Date 2023-11-17
End Date 2024-02-26
Activity Regular Safety and Health Inspection
Number Inspectors 4
Total Hours 68.5
Start Date 2023-09-05
End Date 2023-09-05
Activity Spot Inspection
Number Inspectors 1
Total Hours 10
Start Date 2023-08-08
End Date 2023-08-21
Activity Regular Safety and Health Inspection
Number Inspectors 4
Total Hours 58.5
Start Date 2023-05-17
End Date 2023-05-17
Activity Special Emphasis Programs
Number Inspectors 1
Total Hours 2
Start Date 2023-03-08
End Date 2023-03-08
Activity Regular Safety and Health Inspection
Number Inspectors 1
Total Hours 4
Start Date 2022-06-06
End Date 2022-09-22
Activity Regular Safety and Health Inspection
Number Inspectors 3
Total Hours 60.25
Start Date 2022-04-07
End Date 2022-04-07
Activity Mine Idle Activity
Number Inspectors 1
Total Hours 7
Start Date 2022-02-15
End Date 2022-03-18
Activity Spot Inspection
Number Inspectors 3
Total Hours 17.75
Start Date 2021-10-01
End Date 2021-10-28
Activity Regular Safety and Health Inspection
Number Inspectors 2
Total Hours 44.5
Start Date 2021-04-06
End Date 2021-04-26
Activity Regular Safety and Health Inspection
Number Inspectors 2
Total Hours 92
Start Date 2020-10-01
End Date 2020-12-14
Activity Regular Safety and Health Inspection
Number Inspectors 2
Total Hours 81.5
Start Date 2020-09-28
End Date 2020-09-28
Activity Special Emphasis Programs
Number Inspectors 1
Total Hours 7.5
Start Date 2020-08-07
End Date 2020-08-11
Activity Spot Inspection
Number Inspectors 1
Total Hours 9
Start Date 2020-04-01
End Date 2020-04-16
Activity Regular Safety and Health Inspection
Number Inspectors 3
Total Hours 111.5
Start Date 2020-02-19
End Date 2020-02-19
Activity Special Emphasis Programs
Number Inspectors 1
Total Hours 4
Start Date 2019-11-27
End Date 2020-01-10
Activity Regular Safety and Health Inspection
Number Inspectors 2
Total Hours 26.75

Productions

Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2024
Annual Hours 2032
Annual Coal Prod 0
Avg. Annual Empl. 2
Avg. Employee Hours 1016
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2023
Annual Hours 10786
Annual Coal Prod 0
Avg. Annual Empl. 4
Avg. Employee Hours 2697
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2022
Annual Hours 780
Annual Coal Prod 0
Avg. Annual Empl. 1
Avg. Employee Hours 780
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2021
Annual Hours 1822
Annual Coal Prod 0
Avg. Annual Empl. 1
Avg. Employee Hours 1822
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2020
Annual Hours 4045
Annual Coal Prod 0
Avg. Annual Empl. 3
Avg. Employee Hours 1348
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2019
Annual Hours 6848
Annual Coal Prod 0
Avg. Annual Empl. 4
Avg. Employee Hours 1712
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2018
Annual Hours 5811
Annual Coal Prod 0
Avg. Annual Empl. 6
Avg. Employee Hours 969
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2017
Annual Hours 6889
Annual Coal Prod 0
Avg. Annual Empl. 4
Avg. Employee Hours 1722
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2016
Annual Hours 6732
Annual Coal Prod 0
Avg. Annual Empl. 4
Avg. Employee Hours 1683
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2015
Annual Hours 2698
Annual Coal Prod 0
Avg. Annual Empl. 5
Avg. Employee Hours 540
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2014
Annual Hours 9642
Annual Coal Prod 0
Avg. Annual Empl. 5
Avg. Employee Hours 1928
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2013
Annual Hours 11501
Annual Coal Prod 0
Avg. Annual Empl. 6
Avg. Employee Hours 1917
Sub-Unit Desc OFFICE WORKERS AT MINE SITE
Year 2013
Annual Hours 116
Annual Coal Prod 0
Avg. Annual Empl. 1
Avg. Employee Hours 116
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2012
Annual Hours 13597
Annual Coal Prod 0
Avg. Annual Empl. 6
Avg. Employee Hours 2266
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2011
Annual Hours 13109
Annual Coal Prod 0
Avg. Annual Empl. 6
Avg. Employee Hours 2185
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2010
Annual Hours 8351
Annual Coal Prod 0
Avg. Annual Empl. 4
Avg. Employee Hours 2088
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2009
Annual Hours 8700
Annual Coal Prod 0
Avg. Annual Empl. 4
Avg. Employee Hours 2175
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2008
Annual Hours 10447
Annual Coal Prod 0
Avg. Annual Empl. 5
Avg. Employee Hours 2089
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2007
Annual Hours 10217
Annual Coal Prod 0
Avg. Annual Empl. 5
Avg. Employee Hours 2043
Sub-Unit Desc MILL OPERATION/PREPARATION PLANT
Year 2006
Annual Hours 10244
Annual Coal Prod 0
Avg. Annual Empl. 5
Avg. Employee Hours 2049